Completion of Nadu Nedu components before re-opening of Schools in the State - Instructions issued - regarding.
Circular.No.2453202 /MBNN/2024 Dated.29/05/2024
Ref: Instructions issued in the Webex meeting held on 28.05.2024.
-----xxx-----
In the reference cited, the instructions were issued to the all feld level functionaries to complete all Nadu Nedu components before reopening of schools on 12.06.2024 as detailed below:
Important tasks to be commenced before re-opening of Schools:
• Ensure that all the Nadu Nedu Components ( civil works) are completed by 12th June, 2024 and installation of fxtures like doors windows and GCBs may be done after 12th June.
• In case of Additional Class Rooms eforts should be made to target completion of ACRs up to slab level by 12.06.2024. Only brick work, painting & fnishing shall be taken up after 12th June, 2024).
• DEOs/Additional Project coordinators in the State should utilize TEO (funds) and TEO (material) option for required fund and material mobilization to complete Additional Class Rooms up to Slab level.
• DEOs/APCs shall issue instructions to HMs and MEOs to ensure removal of debris and other construction material from the construction sites to prevent any accidents or injuries to students.
• All the supplied CPM material should be installed and be made functional before the reopening of schools.
2. Hence, All the District Education Ofcers and Additional Project Co-ordinators are instructed to ensure compliance of the above instructions by the concerned feld staf.